Incremental Progress This Past Week

New handicap access ramp.

New handicap access ramp.

This week concrete was poured to finish the handicap access ramps and the benches were installed. Best we can tell the only thing left to complete is fence installation. City staff indicates that "Fence installation was to start Monday."  When we went by Monday morning, there was no one on site, so we will check later this week to see if installation has begun.

Staff also let us know that Montgomery County site inspection to remove tree protection fence and clear the park for opening is scheduled for this Wednesday. After that staff indicate that they have signs to install and minor site work which will be done by next week.

Benches now bolted down.

Benches now bolted down.

That holds out the possibility that we can make the April 2 opening we discussed. We are waiting from word from the City Manager whether this will, in fact, be the opening date.

Check out the rest of the new photos in our Construction Photo Gallery.